Construction is underway to build a connecting bridge between the National Library and the new Archives building. The building is open during construction but there are changes to our services while the work is underway. Read the latest updates.

Updated 23 January 2024

We are open during construction

We are open during construction but there are some changes to our services while the work is underway. Building work will run until October 2024

Reading rooms changes

The reading rooms are open

Pick up all items from Katherine Mansfield Reading Room

All collection items will be delivered to the Katherine Mansfield Reading Room and issued there for reading.

As so many items in the Turnbull collections are one of a kind, we don't allow bags, coats, food or drink, or pens in the Katherine Mansfield Reading Room. We provide lockers and plastic bags for your things.

Collection delivery times

Collection delivery times are as follows.

Day

If you request an item by

Your item will be available from

Monday to Friday

8:30am

10am

Monday to Friday

10:30am

12pm

Monday to Friday

12pm

1:30pm

Monday to Friday

1:30pm

3pm

Monday to Friday

3pm

4:30pm

Friday only

4pm

9am Saturday

Saturday/Sunday

No collection delivery

No collection delivery

He Tohu exhibition

The He Tohu interactive exhibition has been removed and stored. There was a formal blessing by mana whenua Taranaki Whānui.

You can visit the three iconic constitutional documents — He Whakaputanga 1835, Te Tiriti o Waitangi 1840, and The Women’s Suffrage Petition 1893, in He Whakapapa Kōrero (the document room).

Find out more about visiting He Tohu

Tiakiwai Conference Centre

The Tiakiwai Conference Centre has limited availability. There will be changes to floor layouts and venue spaces because of the building works.

While some services will be affected, we're still here to assist you however we can.

Contact Tiakiwai Conference Centre

Events

Check the events page on our website for updates to our event programme.

Check our events

Piano Room closed

The Piano Room will be closed while building works are going on.

What’s happening

A two-level link bridge is being constructed that will connect the new Archives New Zealand building to the National Library building in Wellington. Building work will run from 3 April 2023 until September 2024.

The link bridge is part of Heke Rua Archive building project, which aims to enable greater collaboration between Archives and the Library through shared facilities and public services. 

Heka Rua Archive building project

Collection care during construction

The risks to our collections are low, and we've put measures in place in the collection stores, the He Tohu document room, and the building to ensure their safety. Our collection care staff continue to work with the construction company to address any potential impact on our collections.

General construction noise

Until October 2024, there will be higher levels of noise that will be disruptive to staff and visitors.

Expert opinion is that the noise and vibration will not be harmful to people or collections, but may be irritating or uncomfortable. 

Key construction dates

To help you plan your visit, here’s what’s happening:

  • 10 October 2023 to January 2024 — façade demolition phase 2

  • 1 November 2023 to October 2024 — general construction noise

  • Mid-August to mid-January 2024 — building new classroom space.